#50441 - 12/18/14 09:30 AM add Date stamp on the process and subprocesses
Sami786 Offline
OL Expert

Registered: 01/29/14
Posts: 400
Loc: Home
I think it's best to add date stamp on the processe properties and subprocesses in order to know when each process was created. This will be very helpful when you have many jobs and processes
BEST REGARDS

Top
#50450 - 12/19/14 09:43 AM Re: add Date stamp on the process and subprocesses [Re: Sami786]
Raphael Lalonde Lefebvre Offline
OL Expert

Registered: 10/14/05
Posts: 4956
Loc: Objectif Lune Montreal
Hi Sami786,

Not entirely sure if you actually mean adding a time stamp to know when the process was CREATED(in other words, added to the configuration components), or just a date stamp to know when the process was started and/or finished.

The good news is: you can already have both!

For adding a date when the process was created, you can simply manually put it in the "Information" tab that each processes have. If you double-click on a process in the configuration components, you'll have access to the Information tab, where you can enter any information you want. So you could put a date when the process was created, as well as any other relevant information.

As for knowing when a process is started/finished, the log files already contain that information. The logs can usually be found in:

C:\ProgramData\Objectif Lune\PlanetPress Suite 7\PlanetPress Watch\Log

The log files should contain the information on when a process was started, and when it was completed.

Regards,
Raphaël Lalonde Lefebvre